While you may not see active construction taking place outside at the moment, progress on our building and renovation project is continuing behind the scenes. We have recently received bids for an important next step—installing a new sewer line earlier than originally planned.
Due to challenges with the slope of the current system, it has been determined that running the new sewer line now will allow for a smoother process as we move through each phase of construction. This proactive approach will help prevent complications later on and keep the project moving efficiently.
Construction activity will be picking up again soon. As part of this work, crews will be digging a line from the previous administrative wing all the way to Ada Street. During this time, temporary walkways will be in place to maintain safe access for residents, staff, and visitors. Once the work is completed, all sidewalks will be fully repaired.